Expansion joints for the Jianghai Bridge

Presently, the 35 km long Hong Kong-Zhuhai-Macao Bridge (HZMB) is being constructed over the Pearl River Delta. Since 2009 the HZMB is under construction and planned to be opened for traffic in the autumn of 2017. One of many technical challenges is the Jianghai Bridge, a cable stayed bridge of 700 m main span.

Thereby the steel bridge segments for the HZMB were prefabricated in a factory on land, in order to minimize steel works in situ to the extent possible. This also applies for the Jianghai cable stayed bridge which spans the main shipping lane. While the HZMB usually consists of prefabricated segments of a length of 110 m, the Jianghai Bridge displayed of field lengths of up to 258 m, which called for correspondingly large expansion joints. In order to anchor the expansion joints into the steel bridge segments, at the front ends of the steel end girder openings had to be designed for the purpose of accommodating the support beams of the expansion joints.

Complete preparation for the connection

For the Jianghai Bridge, MAURER designed large expansion joints that were already completely prepared for the steel to steel connection into the bridge deck. In other words, the support beams of the expansion joints not only had to fit into the openings of the steel end girder, but they had to be inserted in one go from the front. The standard procedure of lowering of the expansion joints from above into a block-out was not possible. So for this bridge MAURER designed an expansion joint for a steel connection, which allowed the expansion joint to be inserted in one go.

So, the bars of the expansion joint were inserted in a "tilted" manner into one end of the bridge deck, then lowered into horizontal position, and finally inserted horizontally into the opposite openings of the adjacent bridge deck. Thereafter, the supports just had to be welded to their respective steel deck. This process took only 2-3 days, which for an expansion joint of this size is rather fast.

In the autumn of 2016, each four expansion joints with a displacement capacity of 1,760 mm and 1,200 mm, respectively, were installed at the Jianghai Bridge. Each of the expansion joints has a width of 16.3 m, weighing around 36 tons. They bridge the structural gaps of the 33 m wide bridge in pairs.

Fast installation in only 20 days

The installation of the eight expansion joints took only 20 days. With standard design, that is, skew support beams, the installation time would have taken at least double that long.

The control system of the lamella gaps worked perfectly from day one, because it is irrelevant whether the movement of the bridge is being caused by temperature, wind, or later by traffic. This is a precondition of freedom of maintenance as well as long service life.

Inquiry for further information

Fields marked with a red asterisk * must be completed for the message to be sent.

References

Macau, China, Asia - Chek Lap Kok, Islands, Hong Kong, China (2018)

  • About this
    data sheet
  • Product-ID
    7485
  • Published on:
    25/04/2017
  • Last updated on:
    19/05/2017