Beginning of works: August 2011
Completion: May 2016
Status: completed

Project Type

Location

Location: , , ,
Crosses:
  • Almonte River
Next to: La Plata Bridge (1967)
Coordinates: 39° 41' 10.56" N    6° 27' 40.18" W
Show coordinates on a map

Technical Information

Dimensions

total length 996 m
arch width 6.00 - 19.00 m
rise 67.5 m
arch span 384 m
thickness 4.80 - 6.90 m
superstructure deck depth 3.10 m
span lengths 36 m - 6 × 45 m - 3 × 42 m + 3 × 42 m - 8 × 45 m - 36 m
deck width 14.00 m

Quantities

concrete volume 60 000 m³
prestressing steel 500 t
reinforcing steel 8 250 t
temporary stays 920 t

Materials

superstructure prestressed concrete
piers reinforced concrete
arch reinforced concrete
abutments reinforced concrete
piers on arch reinforced concrete

Advertisement

Relevant Web Sites

Relevant Publications

  • Arribas, David / Cavero, Pedro / Carnero, David / Jiménez, Pablo (2016): Almonte Viaduct. Construction Process. Presented at: Challenges in Design and Construction of an Innovative and Sustainable Built Environment, 19th IABSE Congress Stockholm, 21-23 September 2016, pp. 2282-2289.
  • Arribas, David / Bernal, Pablo / Pérez, José María / González, José Ignacio (2016): Almonte Viaduct. Detailed Design. Presented at: Challenges in Design and Construction of an Innovative and Sustainable Built Environment, 19th IABSE Congress Stockholm, 21-23 September 2016, pp. 2274-2281.
  • Arribas Mazarracín, David / Cavero De Pablo, Pedro / Carnero Pérez, David / Jiménez Guijarro, Pablo (2017): Procedimiento Constructivo del Viaducto sobre el río Almonte. Presented at: VII Congreso Internacional de Estructuras, Congreso de la Asociación Científico-Técnica del Hormigón Estructural (ACHE), A Coruña, 20-22 de junio de 2017.
  • Arenas, Juan José / Capellán, Guillermo / Martínez, Javier / Merino, Emilio / Guil, Ysabel / García-Arias, Pascual (2016): Viaduct over River Almonte. Design and Analysis. Presented at: Challenges in Design and Construction of an Innovative and Sustainable Built Environment, 19th IABSE Congress Stockholm, 21-23 September 2016, pp. 2336-2343.
  • Capellán, Guillermo / Martínez, Javier / Merino, Emilio / García-Arias, Pascual / Arribas, David / Jiménez, Pablo (2016): Viaduct over River Almonte. Site Control and Supervision. Presented at: Challenges in Design and Construction of an Innovative and Sustainable Built Environment, 19th IABSE Congress Stockholm, 21-23 September 2016, pp. 1855-1862.
More publications...
  • About this
    data sheet
  • Structure-ID
    20072092
  • Date created
    06/11/2016
  • Last Update
    02/06/2017