Thomas Francis Meagher Bridge

General Information

Other name(s): River Suir Bridge
Beginning of works: April 2006
Completion: 19 October 2009
Status: in use

Project Type

Location

Location: , ,
,
Crosses:
  • River Suir
Coordinates: 52° 16' 42.32" N    7° 9' 4.54" W
Show coordinates on a map

Technical Information

Dimensions

main span 230 m
length 465 m
span lengths 42.0 m - 66.5 m - 91.5 m - 230.0 m - 35.0 m
number of lanes 2 x 2
deck total width 30.60 m
roadway / carriageway width 2 x (10.50 - 13.50 m)
deck of main span on-center distance between girders 25.60 m
pylon height 112.80 m

Quantities

deck structural steel 2 900 t
concrete volume 3 553 m³
reinforcing steel 925 t
piers concrete volume 545 m³
pylon concrete volume 4 379 m³
stay cables steel for cable-stays 436 t

Materials

pylon reinforced concrete
piers reinforced concrete
deck of main bridge composite steel-reinforced concrete
abutments reinforced concrete

Products, Services & Reports

Robo®Control detects the absence of machine specifications at the component and conveys these to a central computer. There the data are processed a ...

[more]

Modular Expansion Joints can be constructed for any movements, from about 100 mm up to 2,000 mm and more. They allow movements in all 3 directions ...

[more]

Chronology

April 2006

Beginning of works.

19 October 2009

Opened.

Advertisement

Participants

Design
Wind tunnel testing
Contractor
Steel construction
Precastor
Foundations
Stay cables
Prestressing
Expansion joints
Construction supervision

Relevant Web Sites

Relevant Publications

More publications...
  • About this
    data sheet
  • Structure-ID
    20019004
  • Date created
    10/01/2006
  • Last Update
    05/02/2016