General Information
Project Type
Function / usage: |
Motorway bridge / freeway bridge |
---|---|
Structure: |
Box girder bridge |
Material: |
Prestressed concrete bridge |
Construction method: |
main bridge: Balanced cantilever method approach viaducts: Precast segmental construction |
Location
Location: |
Brisbane, Queensland, Australia |
---|---|
Crosses: |
|
Next to: |
Gateway Bridge (1986)
|
Coordinates: | 27° 26' 40.80" S 153° 6' 4.08" E |
Technical Information
Dimensions
main span | 2 x 260 m | |
total length | 1 627 m | |
span lengths | 60 m - 4 x 71 m - 162 m - 2 x 260 m - 162 m - 9 x 71 m - 60 m | |
number of spans | 18 | |
height above valley floor or water | max. 64.5 m | |
deck | width | 27.5 m |
deck of approach viaducts | girder depth | 3.3 m |
deck of main bridge | girder depth | 5 - 15 m |
Cost
cost of construction | Australian dollar 350 000 000 |
Materials
deck |
prestressed concrete
|
---|---|
deck of approach viaducts |
precast prestressed concrete
|
Case Studies and Applied Products
TENSA®MODULAR LR & LR-LS – Modular expansion joints
Modular Expansion Joints can be constructed for any movements, from about 100 mm up to 2,000 mm and more. They allow movements in all 3 directions and rotations around all 3 axes.
[more]Participants
Relevant Web Sites
Relevant Publications
- (2010): Second Gateway Bridge, Brisbane, Australia. Presented at: IABSE Symposium: Large Structures and Infrastructures for Environmentally Constrained and Urbanised Areas, Venice, Italy, 22-24 September 2010, pp. 706-707.
- Twice as nice. In: Bridge Design & Engineering, v. 14, n. 52 (3rd Quarter 2008), pp. 26-27, 31. (2008):
- About this
data sheet - Structure-ID
20017772 - Published on:
12/09/2005 - Last updated on:
05/02/2016