General Information
Project Type
Structure: |
Box girder bridge |
---|---|
Function / usage: |
Road bridge |
Construction method: |
Incremental launching |
Material: |
Steel-reinforced concrete composite bridge |
Location
Location: |
Valence, Drôme (26), Auvergne-Rhône-Alpes, France Soyons, Ardèche (07), Auvergne-Rhône-Alpes, France |
---|---|
Crosses: |
|
Coordinates: | 44° 54' 28.75" N 4° 52' 1.53" E |
Technical Information
Dimensions
total length | 526 m | |
span lengths | 75 m - 3 x 125 m - 75 m | |
number of spans | 5 | |
deck | deck width | 22.10 m |
piers | pier height | max. 13 m |
Quantities
structural steel | 3800 t |
Cost
cost of construction | Euro 24 390 000 |
Materials
deck slab |
reinforced concrete
|
---|---|
girders |
steel
|
Chronology
9 March 2000 | Open call for tender. |
---|---|
6 December 2000 | Contract is awarded. |
November 2001 | Beginning of construction. |
Participants
Owner
Client
Main contractor
Steel construction
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Deck pushes ahead on new Rhone crossing. In: Bridge Design & Engineering, v. 9, n. 31 (2nd Quarter 2003), pp. 8. (2003):
- Un deuxième pont à Valence. In: Le Moniteur des Travaux Publics et du Bâtiment, n. 5277 (14 January 2005), pp. 28.
- Le deuxième pont sur le Rhône à Valence. In: Travaux, n. 793 (January 2003), pp. 30-36. (2003):
- Nouveau pont sur le Rhône à Valence. In: Bulletin ponts métalliques, n. 23 ( 2004), pp. 202-219. (2004):
- About this
data sheet - Structure-ID
20004088 - Published on:
03/07/2002 - Last updated on:
05/04/2016