General Information
Other name(s): | Nouveau tunnel routier du Lioran |
---|---|
Beginning of works: | 2003 |
Completion: | 2007 |
Duration of works: | 22 months |
Status: | in use |
Project Type
Structure: |
Tunnel |
---|---|
Function / usage: |
Road tunnel |
Construction method: |
Drilling and blasting |
Location
Location: |
Le Lioran, Laveissière, Cantal (15), Auvergne-Rhône-Alpes, France |
---|---|
Address: | N122 |
To replace: |
Lioran Road Tunnel (1848)
|
Coordinates: | 45° 5' 12.83" N 2° 44' 39.81" E |
Coordinates: | 45° 4' 40.49" N 2° 43' 50.22" E |
Technical Information
Dimensions
height | 4.50 m | |
total length | 3 470 m | |
clearance | 4.30 m | |
tunnel length | 1 515 m | |
tunnel section area | 100 m² | |
roadway / carriageway width | 2 x 3.50 m |
Quantities
concrete volume | 40 000 m³ | |
shotcrete | 6 000 m³ | |
explosives used | 173 t |
Cost
cost of construction | Euro 78 570 000 |
Chronology
July 2003 — End of 2005 | Breakthrough. |
---|---|
End of 10 2006 | Expected completion of the concrete cover of the tunnel structure. |
16 2007 | Opened to traffic |
Participants
Owner
Client
- Arrondissement interdépartemental des ouvrages d'art
- Direction Départementale de l'Equipement du Cantal
Civil works
Earthworks
Water proofing
Relevant Web Sites
Relevant Publications
- Le regain d'un métier historique de Sogea Construction (tunnel du Lioran, tunnel du Bois-de-Peu, le TIMA, A86 Ouest). In: Travaux, n. 822 (September 2005), pp. 96-103. (2005):
- Tunnel du Lioran (15). Forage à l'explosif en site sensible. In: Prévention BTP, n. 72 (March 2005), pp. 16-21. (2005):
- Le tunnel du Lioran est percé. In: Le Moniteur des Travaux Publics et du Bâtiment, n. 5300 (24 June 2005), pp. 45. (2005):