General Information
Other name(s): | Transjurane |
---|---|
Completion: | 2017 |
Status: | in use |
Project Type
Function / usage: |
Motorway / Freeway / Interstate |
---|
Location
km | Name |
59.485 |
Technical Information
Dimensions
total length | 85 km |
Cost
cost of construction | Swiss Franc 5 600 000 000 |
Chronology
11 November 2011 | Opening of the 4.6 km-long section from Boncourt to Bure. |
---|---|
5 November 2013 | Opening of the 3.2 km-long section from Moutier Sud to Court. |
21 August 2014 | Opening of the 8.3 km-long section from Bure to Porrentruy west |
5 December 2016 | Opening of the 4.9 km-long section from Delémont to Choindez |
3 April 2017 | Opening of the 9.1 km-long section from Court to Loveresse. |
Participants
Currently there is no information available about persons or companies having participated in this project.
Relevant Web Sites
Relevant Publications
- The A16 Transjurane Highway: Architectural Acupuncture. In: (2012): Cooperation. Birkhäuser, Basel (Switzerland), ISBN 9783034610551, pp. 169-174. (2012):
- A16 Transjurane: ulteriori novità novembrine. In: Strade e Autostrade, v. 18, n. 103 (January 2014), pp. 18-19. (2014):
- Die Autobahn A16 Transjurane: Architektonische Akupunkturen. In: (2012): Kooperation. Birkhäuser, Basel (Switzerland), ISBN 978-3-0346-1056-8, pp. 169-174. (2012):
- Due nuovi passi avanti per la Transjurane. In: Strade e Autostrade, v. 16, n. 91 (January 2012), pp. 16. (2012):
- Due nuovi passi avanti per la Transjurane. In: Strade e Autostrade, v. 16, n. 91 (January 2012). (2012):
- About this
data sheet - Structure-ID
10000497 - Published on:
08/04/2004 - Last updated on:
23/01/2022