Selecting project delivery methods for water treatment plants

Author(s):



Medium: journal article
Language(s): English
Published in: Engineering, Construction and Architectural Management, , n. 4, v. 27
Page(s): 936-951
DOI: 10.1108/ecam-06-2019-0308
Abstract:

Purpose

The purpose of this paper is to identify key project delivery method selection factors to assist water industry decision-makers in selecting the most appropriate delivery method for their water treatment plant projects.

Design/methodology/approach

The selection factors were identified by compiling and validating key project delivery selection factors across various industries through an extensive literature review and two industry expert workshops. This resulted in the development of a web-based decision-support tool to facilitate project delivery method selection within the water industry.

Findings

The research effort led to the identification of 13 key project delivery method selection factors (seven primary factors and six secondary factors) for water treatment plant projects. These factors were utilized to develop EXPRSS-TP, a pioneering web-based project delivery method decision-support tool for the water industry.

Practical implications

A project delivery method selection process is typically an informal process that may range from days to weeks at a time. Based on this work, the assessment can now be completed in about one hour and provides decision-makers with the most favorable delivery method for their project. And with the new tool that encompasses the new knowledge, not only is the decision reached at an accelerated pace, EXPRSS-TP also documents the entire selection process, allowing for a written and retained record of this key decision and its procedure.

Originality/value

This paper contributes to the exisiting body of knowledge by identifying key project delivery selection factors across numerous industries, assessing and combining them, and finally incorporating them into one comprehensive process. EXPRSS-TP improves the traditional project delivery method selection process and provides evidence-based project delivery method selection recommendations.

Structurae cannot make the full text of this publication available at this time. The full text can be accessed through the publisher via the DOI: 10.1108/ecam-06-2019-0308.
  • About this
    data sheet
  • Reference-ID
    10576847
  • Published on:
    26/02/2021
  • Last updated on:
    26/02/2021
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine