General Information

Beginning of works: February 1996
Completion: November 1999
Duration of works: 37 months
Status: in use

Project Type

Structure: Lined tunnel
Function / usage: Road tunnel

Location

Location: , , , ,
, , , ,
For:
  • Autobahn A4
Part of:
Coordinates: 51° 12' 53.33" N    14° 48' 42.79" E
Coordinates: 51° 13' 9.05" N    14° 51' 29.57" E
Show coordinates on a map

Technical Information

Dimensions

clear interior profile 9.65 m x 6.45 m
tunnel length 2 x 3 300 m
number of lanes 2 x 2
number of tubes 2

Quantities

concrete volume 77 385 m³
volume of extracted material 568 425 m³
water proofing 54 872 m²
shotcrete 37 113 m³
number of anchors 27 365

Cost

cost of construction German Mark 137 000 000

Materials

tunnel structure reinforced concrete

Chronology

18 May 2013

Roughly 600 meters away from the eastern tunnel portal a truck fire occurs in the southern tube of the Köningshainer Berge tunnel. After the fire, concrete spalling is observed in the affected area.

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20001189
  • Published on:
    17/12/2000
  • Last updated on:
    06/05/2016
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine