General Information
Other name(s): | Tunnel routier de Toulon |
---|---|
Beginning of works: | 1993 |
Completion: | 2 July 2002 |
Status: | in use |
Project Type
Structure: |
Tunnel |
---|---|
Function / usage: |
Road tunnel |
Location
Location: |
Toulon, Var (83), Provence-Alpes-Côte d'Azur, France |
---|---|
Next to: |
Toulon Road Tunnel (2014)
|
Coordinates: | 43° 7' 12.93" N 5° 56' 57.69" E |
Coordinates: | 43° 7' 37.68" N 5° 54' 57.38" E |
Technical Information
Dimensions
tunnel length | 3 333 m |
Cost
cost of construction | Euro 350 000 000 |
Chronology
End of 1991 | The construction site is launched. |
---|---|
April 1993 | Actual start of works. |
1996 | A partial collapse interrupts the construction for about 20 months. |
6 July 2002 | The first tube is inaugurated while a second one is still in geotechnical planning. |
Participants
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- 36 000 t d'acier assemblées sur les rives du Tarn. In: Le Moniteur des Travaux Publics et du Bâtiment, n. 5210 (3 October 2003), pp. 99. (2003):
- Les accès: trémies et tranchées couvertes. In: Travaux, n. 806 (March 2004), pp. 31-34. (2004):
- Additif 2002 aux recommandations CLOUTERRE 1991. Pour la conception, le calcul, l'exécution et le contrôle des soutènements réalisés par clouage des sols. Presses de l'Ecole des Ponts et Chaussées, Paris (France), 2002.
- Analyse du fonctionnement de prévoûtes en béton. Appliction au cas du tunnel de Toulon. Presented at: AFTES – Paris 25-28 octobre 1999, pp. 73-80. (1999):
- Analyse et prévision des tassements de surface pendant le creusement du tunnel nord de la traversée souterraine de Toulon. In: Bulletin des Laboratoires des Ponts et Chaussées, n. 237 (March - April 2002), pp. 5-36. (2002):
- About this
data sheet - Structure-ID
20004512 - Published on:
16/08/2002 - Last updated on:
25/08/2022