General Information
Official designation: | VIA 214 |
---|---|
Beginning of works: | October 2012 |
Completion: | July 2014 |
Duration of works: | 18 months |
Status: | completed |
Project Type
Function / usage: |
High-speed rail bridge |
---|---|
Structure: |
Single-cell box girder bridge |
Material: |
Steel-reinforced concrete composite bridge |
Construction method: |
Longitudinal launching |
Structure: |
Haunched girder bridge |
Material: |
Structurae Plus/Pro - Subscribe Now! |
Location
Location: |
Neuville-sur-Sarthe, Sarthe (72), Pays de la Loire, France |
---|---|
Crosses: |
|
Part of: | |
Coordinates: | 48° 5' 45.17" N 0° 12' 9.06" E |
Technical Information
Dimensions
width | 12.64 m | |
total length | 433 m | |
span lengths | 32 m - 5 x 44 m - 56.5 m - 68 m - 56.5 m | |
number of spans | 9 | |
girder depth | 3.25 - 4.75 m | |
piers | number | 2 x 8 |
Quantities
structural steel | 1 572 t | |
concrete volume | 7 490 m³ | |
reinforcing steel | 1 001 t | |
sheet piling | 2 869 m² | |
total length of piles | 176 m |
Design Loads
design speed | 350 km/h |
Materials
piers |
reinforced concrete
|
---|---|
deck slab |
reinforced concrete
|
abutments |
reinforced concrete
|
girders |
steel
|
Participants
Conceding authority
Owner
Architecture
- Jean-Pierre Duval (architect)
-
Architecture NEEL
- Fabrice Néel (architect)
Contractor
Steel construction
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Les ouvrages d'art de la LGV BPL. In: Travaux, n. 912 (January 2015), pp. 82-88. (2015):
- About this
data sheet - Structure-ID
20070827 - Published on:
04/03/2016 - Last updated on:
26/08/2024