Beginning of works: February 2008
Completion: August 2010
Duration of works: 31 months
Status: in use

Project Type

Location

Location: , , ,
Part of:
Coordinates: 50° 58' 42" N    10° 29' 3" E
Show coordinates on a map

Technical Information

Dimensions

total length 414.00 m
span lengths 42.00 m - 55.00 m - 70.00 m - 80.00 m - 70.00 m - 55.00 m - 42.00 m
number of spans 7
horizontal radius of curvature 2 500 m
bridge surface 14 904 m²
superelevation 3.5%
deck girder depth 2.70 - 3.735 m

Quantities

deck concrete volume 6 376 m³
prestressing steel 53 t
reinforcing steel 1 792 t
substructure concrete volume 9 040 m³
reinforcing steel 1 012 t

Cost

cost of construction Euro 27 000 000

Materials

piers reinforced concrete
deck slab prestressed concrete
abutments reinforced concrete
girders steel

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20064773
  • Published on:
    20/03/2013
  • Last updated on:
    06/10/2016
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine