General Information
Other name(s): | Viaduc de Miribel |
---|---|
Completion: | 1993 |
Duration of works: | 17 months |
Status: | in use |
Project Type
Structure: |
Box girder bridge |
---|---|
Function / usage: |
High-speed rail bridge |
Construction method: |
Incremental launching |
Material: |
Prestressed concrete bridge |
Location
Location: |
Nievroz, Ain (01), Auvergne-Rhône-Alpes, France Jons, Rhône (69), Auvergne-Rhône-Alpes, France |
---|---|
Crosses: |
|
Part of: | |
Coordinates: | 45° 48' 30.29" N 5° 3' 49.04" E |
Technical Information
Dimensions
main span | 53 m | |
total length | 535 m |
Cost
cost of construction | French Franc 53 600 000 |
Materials
deck |
prestressed concrete
|
---|
Participants
Owner
Client
Checking engineering
Main contractor
Relevant Web Sites
There currently are no relevant websites listed.
- About this
data sheet - Structure-ID
20007880 - Published on:
17/01/2003 - Last updated on:
05/02/2016