General Information
Name in local language: | Lützelbachtalbrücke |
---|---|
Beginning of works: | November 2013 |
Completion: | 28 June 2018 |
Status: | in use |
Project Type
Function / usage: |
Motorway bridge / freeway bridge |
---|---|
Structure: |
Box girder bridge |
Material: |
Steel-reinforced concrete composite bridge Structurae Plus/Pro - Subscribe Now! |
Location
Location: |
Dillenburg, Lahn-Dill-Kreis, Hesse, Germany |
---|---|
Carries: |
|
Replaces: |
Lützelbach Viaduct
|
Coordinates: | 50° 43' 6.49" N 8° 17' 16.89" E |
Technical Information
Dimensions
total length | ca. 270 m | |
span lengths | 52.00 m - 57.80 m - 58.90 m - 57.80 m - 43.50 m | |
number of spans | 5 | |
bridge surface | 9 747 m² | |
deck | deck width | 36.10 m |
girder depth | 3.60 m | |
piers | height | 43.52 m |
Quantities
substructure | concrete volume | 7 900 m³ |
reinforcing steel | 1 040 t | |
superstructure | structural steel | 2 926 t |
concrete volume | 4 400 m³ | |
reinforcing steel | 950 t |
Design Loads
live load | LM 1 (DIN EN 1991-2) | |
military load class | MLC 100 & MLC 50/50 (STANAG) |
Cost
cost of construction | Euro 35 000 000 |
Materials
piers |
reinforced concrete
(C 30/37)
|
---|---|
deck slab |
reinforced concrete
(C 35/45)
|
abutments |
reinforced concrete
(C 30/37)
|
girders |
steel
(S 355)
|
Participants
Owner
Client
Design
Structural engineering
Soil investigation report
Checking engineering
- Ekkehard Fehling (checking engineer)
Contractor
Steel construction
Construction management
Site supervision
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Brücken und Tunnel der Bundesfernstraßen 2019. Bundesministerium für Verkehr und digitale Infrastruktur, Berlin (Germany), 2019, pp. 63-78.
- About this
data sheet - Structure-ID
20079086 - Published on:
04/02/2020 - Last updated on:
04/02/2020