0
  • DE
  • EN
  • FR
  • International Database and Gallery of Structures

Advertisement

Building bridges from thin-walled precast elements

 Building bridges from thin-walled precast elements
Author(s): , , , ,
Presented at IABSE Symposium: Challenges for Existing and Oncoming Structures, Prague, Czech Republic, 25-27 May 2022, published in , pp. 1008-1012
DOI: 10.2749/prague.2022.1008
Price: € 25.00 incl. VAT for PDF document  
ADD TO CART
Download preview file (PDF) 0.13 MB

In the construction of Lafnitz Bridge and Lahnbach Bridge thin-walled precast concrete girders with an U-shaped cross-section were used in order to reduce the weight during the construction process...
Read more

Bibliographic Details

Author(s): (TU Wien, Vienna, AT)
(TU Wien, Vienna, AT)
(TU Wien, Vienna, AT)
(TU Wien, Vienna, AT)
(TU Wien, Vienna, AT)
Medium: conference paper
Language(s): English
Conference: IABSE Symposium: Challenges for Existing and Oncoming Structures, Prague, Czech Republic, 25-27 May 2022
Published in:
Page(s): 1008-1012 Total no. of pages: 5
Page(s): 1008-1012
Total no. of pages: 5
DOI: 10.2749/prague.2022.1008
Abstract:

In the construction of Lafnitz Bridge and Lahnbach Bridge thin-walled precast concrete girders with an U-shaped cross-section were used in order to reduce the weight during the construction process. The usage of light-weight girders was advantageous because the girders were erected in the vertical position and rotated into the final horizontal position during the first application of the balanced lowering method. After filling of the girders with in-situ concrete the webs of the bridges were com- pleted. On top of the webs a deck slab was cast using a formwork carriage. While the application of the balanced lowering method permitted a fast construction of the webs, the production of the deck slab with a formwork carriage was a slow process. Therefore a method for the fast production of the deck slab was developed. In this new method precast slab elements, which are stiffened by cross-beams, are placed on top of the webs. This enables a fast construction of post-tensioned con- crete bridges with a plate girder cross-section.

Keywords:
thin-walled sustainable Post-tensioned bridge precast deck slab element balanced lowering method precast girder
Copyright: © 2022 International Association for Bridge and Structural Engineering (IABSE)
License:

This creative work is copyrighted material and may not be used without explicit approval by the author and/or copyright owner.