General Information
Name in local language: | Pont Jacques-Chaban-Delmas |
---|---|
Other name(s): | Bacalan-Bastide Bridge |
Beginning of works: | 2009 |
Completion: | 15 March 2013 |
Duration of works: | 36 months |
Status: | in use |
Project Type
Function / usage: |
Road bridge |
---|---|
Structure: |
Vertical lift bridge |
Function / usage: |
Tramway, light or metro rail bridge |
Structure: |
Girder bridge |
Material: |
Steel bridge |
Support conditions: |
for registered users |
Material: |
Structurae Plus/Pro - Subscribe Now! |
Location
Location: |
Bordeaux, Gironde (33), Nouvelle-Aquitaine, France |
---|---|
Crosses: |
|
See also: |
Control Tower for Jacques Chaban-Delmas Bridge (2013)
|
Coordinates: | 44° 51' 29.78" N 0° 33' 6.61" W |
Technical Information
Dimensions
total length | 575 m | |
clearance | max. 55 m | |
main bridge | ||
---|---|---|
width | 45 m | |
length | 430 m | |
length of movable section | 117 m | |
pylons | height | 87 m |
number | 4 |
Quantities
concrete volume | 40 000 m³ |
Cost
cost of construction | Euro 117 626 000 |
Materials
superstructure |
steel
|
---|---|
towers |
reinforced concrete
|
abutments |
reinforced concrete
|
Excerpt from Wikipedia
The Pont Jacques Chaban-Delmas is a vertical-lift bridge over the Garonne in Bordeaux, France. It was inaugurated on 16 March 2013 by President François Hollande and Alain Juppé, mayor of Bordeaux. Its main span is 110 m (361 ft) long. As of 2013, it is the longest vertical-lift bridge in Europe. It is named in honour of Jacques Chaban-Delmas, a former Prime Minister of France and a former mayor of Bordeaux.
Text imported from Wikipedia article "Pont Jacques Chaban-Delmas" and modified on July 23, 2019 according to the CC-BY-SA 4.0 International license.
Participants
Owner
Design
-
egis jmi
- Nabil Yazbeck (designer)
Architecture
-
Architecture et Ouvrages d'art
- Charles Lavigne (architect)
- Thomas Lavigne (architect)
- Christophe Chéron (architect)
Structural engineering
Consulting engineers
- Jean Muller International
- Hardesty & Hanover
- Michel Virlogeux (consulting engineer)
Main contractor
Co-contractor
Lighting design
Relevant Web Sites
Relevant Publications
- Aux portes de Bordeaux, un pont se lève. In: Travaux, n. 896 (April 2013), pp. 126-130. (2013):
- Communauté urbaine de Bordeaux. Feu vert pour le pont Bacalan-Bastide. In: Le Moniteur des Travaux Publics et du Bâtiment, n. 5416 (14 September 2007), pp. 53. (2007):
- (2015): The New Lifting Bridge in Bordeaux, France - Mechanism Design Code Constraints and Freedoms. Presented at: IABSE Conference: Structural Engineering: Providing Solutions to Global Challenges, Geneva, Switzerland, September 2015, pp. 686-692.
- Il viadotto Chaban-Delmas a Bordeaux. In: Strade e Autostrade, v. 17, n. 100 (July 2013), pp. 96-99. (2013):
- About this
data sheet - Structure-ID
20019373 - Published on:
07/02/2006 - Last updated on:
27/01/2021