General Information
Project Type
Function / usage: |
High-speed rail line |
---|
Location
km | Name |
Technical Information
Dimensions
total length | 102 km | |
embankment | 9 000 000 m³ | |
number of road bridges | ca. 61 | |
number of rail bridges | ca. 32 | |
number of hydraulic structures | ca. 70 | |
number of cut-and-cover tunnels | 8 | |
number of bored tunnels | 1 | |
Lot 42.02/49.03 | ||
---|---|---|
total length | 280 m | |
embankment | 37000 m³ | |
period of construction (in months) | 12 | |
Lot 42.10 | ||
total length | 2463 m | |
embankment | 300 000 m³ | |
period of construction (in months) | 17 | |
Lot 42.30 | ||
total length | 204 m | |
embankment | 70000 m³ | |
period of construction (in months) | 17 | |
Lot 42.40 | ||
total length | 515 m | |
embankment | 16760 m³ | |
period of construction (in months) | 12 | |
Lot 42.50 | ||
total length | 361 m | |
embankment | 50000 m³ | |
period of construction (in months) | 17 | |
Lot 42.60 | ||
total length | 874 m | |
embankment | 90000 m³ | |
period of construction (in months) | 22 | |
Lot 43A | ||
total length | 18 370 m | |
embankment | 1730000 m³ | |
period of construction (in months) | 23 | |
Lot 43B | ||
total length | 2 700 m | |
embankment | 145000 m³ | |
period of construction (in months) | 29 | |
Lot 43C | ||
total length | 2 198 m | |
embankment | 137000 m³ | |
period of construction (in months) | 30 | |
Lot 44 | ||
total length | 43 000 m | |
embankment | 4600000 m³ | |
period of construction (in months) | 23 | |
Lot 45 | ||
total length | 1400 m | |
embankment | 1360000 m³ | |
period of construction (in months) | 20 | |
Lot 46A | ||
total length | 3400 m | |
embankment | 550 000 m³ | |
period of construction (in months) | 40 | |
Lot 46B | ||
total length | 2 900 m | |
embankment | 65000 m³ | |
period of construction (in months) | 36 | |
Lot 46C | ||
total length | 4000 m | |
embankment | 202 000 m³ | |
period of construction (in months) | 25 | |
Lot 49.06 | ||
total length | 420 m | |
embankment | 64000 m³ | |
period of construction (in months) | 20 | |
Lot 49.13 | ||
total length | 400 m | |
embankment | 50000 m³ | |
period of construction (in months) | 18 | |
Lot 49.15 | ||
total length | 150 m | |
embankment | 800 m³ | |
period of construction (in months) | 9 | |
Lot 49.23 | ||
total length | 340 m | |
embankment | 52000 m³ | |
period of construction (in months) | 18 |
Quantities
excavated material | 16 000 000 m³ | |
Lot 42.02/49.03 | ||
---|---|---|
concrete volume | 2800 m³ | |
reinforcing steel | 360 t | |
Lot 42.10 | ||
concrete volume | 45 110 m³ | |
reinforcing steel | 3 900 t | |
volume of extracted material | 1 700 000 m³ | |
Lot 42.30 | ||
concrete volume | 35100 m³ | |
reinforcing steel | 2900 t | |
volume of extracted material | 145000 m³ | |
Lot 42.40 | ||
concrete volume | 86570 m³ | |
reinforcing steel | 6695 t | |
volume of extracted material | 167700 m³ | |
Lot 42.50 | ||
concrete volume | 12190 m³ | |
reinforcing steel | 1236 t | |
volume of extracted material | 110000 m³ | |
Lot 42.60 | ||
concrete volume | 40760 m³ | |
reinforcing steel | 3890 t | |
volume of extracted material | 145000 m³ | |
Lot 43A | ||
concrete volume | 21000 m³ | |
reinforcing steel | 2100 t | |
volume of extracted material | 1450000 m³ | |
Lot 43B | ||
concrete volume | 34400 m³ | |
reinforcing steel | 5450 t | |
volume of extracted material | 450000 m³ | |
Lot 43C | ||
concrete volume | 63000 m³ | |
reinforcing steel | 6600 t | |
volume of extracted material | 900000 m³ | |
Lot 44 | ||
concrete volume | 48500 m³ | |
reinforcing steel | 4520 t | |
volume of extracted material | 8850000 m³ | |
Lot 45 | ||
concrete volume | 25000 m³ | |
reinforcing steel | 2800 t | |
volume of extracted material | 690 000 m³ | |
Lot 46A | ||
concrete volume | 43000 m³ | |
reinforcing steel | 8000 t | |
volume of extracted material | 300 000 m³ | |
Lot 46B | ||
concrete volume | 90000 m³ | |
reinforcing steel | 2400 t | |
volume of extracted material | 300 000 m³ | |
Lot 46C | ||
concrete volume | 88000 m³ | |
reinforcing steel | 7000 t | |
volume of extracted material | 450 000 m³ | |
Lot 49.06 | ||
concrete volume | 6300 m³ | |
reinforcing steel | 1300 t | |
volume of extracted material | 60000 m³ | |
Lot 49.13 | ||
concrete volume | 2600 m³ | |
reinforcing steel | 350 t | |
volume of extracted material | 4000 m³ | |
Lot 49.15 | ||
concrete volume | 2500 m³ | |
reinforcing steel | 220 t | |
volume of extracted material | 10000 m³ | |
Lot 49.23 | ||
concrete volume | 5600 m³ | |
reinforcing steel | 530 t | |
volume of extracted material | 2000 m³ |
Cost
Lot 42.02/49.03 | ||
---|---|---|
cost of lot | French Franc 25 000 000 | |
Lot 42.10 | ||
cost of lot | French Franc 256 000 000 | |
Lot 42.30 | ||
cost of lot | French Franc 126 000 000 | |
Lot 42.40 | ||
cost of lot | French Franc 201 000 000 | |
Lot 42.50 | ||
cost of lot | French Franc 38 000 000 | |
Lot 42.60 | ||
cost of lot | French Franc 128 000 000 | |
Lot 43A | ||
cost of lot | French Franc 314 000 000 | |
Lot 43B | ||
cost of lot | French Franc 200 000 000 | |
Lot 43C | ||
cost of lot | French Franc 352 000 000 | |
Lot 44 | ||
cost of lot | French Franc 743 000 000 | |
Lot 45 | ||
cost of lot | French Franc 244 000 000 | |
Lot 46A | ||
cost of lot | French Franc 400 000 000 | |
Lot 46B | ||
cost of lot | French Franc 300 000 000 | |
Lot 46C | ||
cost of lot | French Franc 295 000 000 | |
Lot 49.06 | ||
cost of lot | French Franc 53 000 000 | |
Lot 49.13 | ||
cost of lot | French Franc 25 000 000 | |
Lot 49.15 | ||
cost of lot | French Franc 12 000 000 | |
Lot 49.23 | ||
cost of lot | French Franc 31 000 000 |
Excerpt from Wikipedia
The LGV Interconnexion Est is a short French high-speed rail line that connects the LGV Nord and LGV Sud-Est through suburbs of Paris. Opened in 1994, it consists of three branches, which begin at Coubert:
- west branch: towards Paris and western France, terminating at Valenton
- north branch: towards northern France, London and Brussels, joining the LGV Nord at Vémars
- south branch: towards southeastern France, joining the LGV Sud-Est at Moisenay
The south and west branches are now shared with the LGV Sud-Est line.
Maximum line-speed throughout is 300km/h (186mph) although nearly all services call at Aéroport Charles de Gaulle 2 TGV and Marne-la-Vallée – Chessy in which, of course, speed is gradually reduced to allow trains to stop at each station.
Route
Starting from the south (LGV Sud-Est or LGV Atlantique), the line begins at Coubert junction and heads northeast. Near Tournan, there is a link to the Paris-Coulommiers line. Further north, Marne-la-Vallée – Chessy station (transfer to the RER A) serves the new town of Marne-la-Vallée and Disneyland Paris theme parks. Near Claye-Souilly, two links under construction will join the line to the LGV Est. The route next serves Aéroport Charles de Gaulle 2 TGV station (transfer to the RER B and air transport). Shortly thereafter, the line joins the LGV Nord at Vémars junction.
Journey times
- Lille-Roissy CDG 0:50
- London - Marne-la-Vallee - Chessy (for Disneyland Paris) 2:43
- Lille-Lyon 2:50
- Lille-Nantes 3:50
- Lille-Grenoble 4:25
- Lille-Marseille 4:30
- Lille-Bordeaux 5:00
- Brussels-Lyon 3:40
- Brussels-Marseilles 5:25
- Brussels-Valence 4:30
- Brussels-Rennes 4:50
- Brussels-Montpellier 5:40
Expansion
- The construction of a suburban line along the LGV between Villeparisis and Vémars is under consideration. This project could have two possible purposes: to serve Roissy airport from Paris (as an alternative to the CDG Express); or to be the beginning of a western line linking Creil to Meaux, Marne-la-Vallée and Melun.
- It has also been proposed to complement the Interconnexion Est with an LGV Interconnexion Sud or LGV Interconnexion Ouest.
- In November 2010, RFF began formal studies of a link from the Interconnexion Est to the Paris - Creil - Amiens line.
Text imported from Wikipedia article "LGV Interconnexion Est" and modified on July 22, 2019 according to the CC-BY-SA 4.0 International license.
Participants
- Bec Frères S.A.
- Bilfinger Berger SE
- Dumez
- Groupe Razel
- GTM Construction
- Guintoli
- Levaux
- Nord France
- RCFC Urbaine
- SEEE
- Bec Frères S.A.
- Bilfinger Berger SE
- Dumez
- Groupe Razel
- GTM Construction
- Guintoli
- Levaux
- Nord France
- RCFC Urbaine
- SEEE
- André Borie
- Bouygues Construction
- Dragages et Travaux Publics Terrassement
- Montcocol
- Muller Frères
- SOGEA
- Bouygues Construction
- Campenon Bernard
- Demathieu et Bard
- Dragages et Travaux Publics Terrassement
- Muller Frères
- Nord France
- Ballot
- Chantiers Modernes
- EI Entreprise Industrielle
- Gagneraud Construction
- Groupe Razel
- Prigent
- Valérian
- Baudin-Châteauneuf
- Bouygues Construction
- Demathieu et Bard
- Dragages et Travaux Publics Terrassement
- Eiffel Construction Metallique
- Etablissements J. Richard Ducros
- Muller Travaux Publics
- Prigent
Relevant Web Sites
Relevant Publications
- Aéroport de Roissy-Charles-de-Gaulle. La traversée de la piste 2 par le TGV et le RER. In: Travaux, n. 681 (November 1992), pp. 60-64. (1992):
- Interconnexion des TGV en région Île-de-France. Déroulement des études géologiques et géotechniques. In: Travaux, n. 652 (April 1990), pp. 1-8. (1990):
- La jonction Est des TGV en Île-de-France. Un atout majeur pour l'Europe. In: Travaux, n. 675 (April 1992), pp. 107-112. (1992):