General Information
Other name(s): | Ferrovia Vigezzina |
---|---|
Beginning of works: | 1912 |
Completion: | 25 November 1923 |
Status: | in use |
Project Type
Function / usage: |
Railroad (railway) line |
---|
Location
km | Name |
Technical Information
Dimensions
total length | 52.183 km | |
number of bridges | 83 | |
number of tunnels | 31 | |
longitudinal slope | max. 6% |
Chronology
1909 — 1910 | Project approval. |
---|---|
1912 | Start of works on the Italian side. |
1913 | Start of works on the Swiss side. |
1914 — 1916 | Various interruptions in construction due to World War I. |
1921 | Construction resumes. |
27 March 1923 | The line is joined from the Swiss and Italian sides at Santa Maria Maggiore. |
25 November 1923 | Inauguration of the line. |
Notes
Of the line 32.283 km are located in Italy and the remaining 19.900 km are in Switzerland. It is a narrow-gauge line with 1.000 m width.
Participants
Currently there is no information available about persons or companies having participated in this project.
Relevant Web Sites
There currently are no relevant websites listed.
- About this
data sheet - Structure-ID
10056180 - Published on:
03/04/2010 - Last updated on:
06/01/2024