General Information

Beginning of works: 2002
Completion: 2005
Status: in use

Project Type

Structure: Box girder bridge
Function / usage: Road bridge
Material: Prestressed concrete bridge
Construction method: Precast segmental construction

Location

Location: , , ,
, , ,
Address: Route 35
Crosses:
  • Raritan River
Replaces: Route 35 Victory Bridge (1926)
Coordinates: 40° 30' 26.31" N    74° 17' 31.45" W
Show coordinates on a map

Technical Information

Dimensions

main span 134.11 m
total length 1 210.36 m

Cost

cost of construction United States dollar 109 121 442

Materials

deck precast prestressed concrete

Chronology

8 June 2004

Opening of first bridge.

December 2005

Expected completion of second bridge.

Notes

The first structure is constructed west of the existing Rt. 35 Victory Bridge. Once that bridge is complete traffic is relocated onto the new structure and then the original bridge is demolished. After demolition is complete, the second structure is to be built where the existing bridge is now located.

Relevant Web Sites

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20012539
  • Published on:
    26/07/2004
  • Last updated on:
    31/03/2021
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine