General Information
Completion: | 24 August 1837 |
---|---|
Status: | in use |
Project Type
Function / usage: |
Railroad (railway) line |
---|
Location
km | Name |
0 | |
0.690 | |
4.206 | |
10.314 | |
14.400 | |
20.477 |
Technical Information
Dimensions
length | 20.4 km | |
number of tracks | 2 | |
longitudinal slope | max. 35 ‰ | |
track gauge | 1 435 mm |
Participants
Current owner
Owner
Engineering
- Christophe Stéphane Mony [Flachat] (engineer)
- Eugène Flachat (engineer)
- Gabriel Lamé (engineer)
- Emile Clapeyron (engineer)
Relevant Web Sites
Relevant Publications
- Le rail en France. Les 80 premières lignes. 1828-1851. Editeurs François et Maguy Palau, Paris (France), pp. 47, 145-148. (1995):
- About this
data sheet - Structure-ID
10001008 - Published on:
20/11/2006 - Last updated on:
28/05/2021