General Information

Beginning of works: 1998
Completion: 16 October 2001
Status: in use

Project Type

Location

Location: ,
Connects to: Malampaya III Platform (2015)
Location description:

The platform is located near Palawan Island in the South China Sea.

Coordinates: 11° 51' 41" N    119° 18' 50" E
Show coordinates on a map

Technical Information

Quantities

concrete volume 34 000 m³
reinforcing steel 12 000 t

Chronology

June 1996
— July 1996

Feasibility study.

April 1998
— June 1998

Front-end engineering study.

July 1998
— August 1998

Tender.

25 September 1998

Contract awarded to Malampaya CGS Alliance (Arup Energy, John Holland, Van Oord)

November 1998
— January 1999

Site clearance at Subic Bay (Philippines) for construction on-shore in a dry dock.

December 1998
— March 1999

Construction of casting basin.

March 1999
— October 1999

Base slab construction.

June 1999
— December 1999

Caisson wall construction.

August 1999
— January 1999

Caisson roof construction.

September 1999
— February 2000

Shaft construction.

October 1999
— March 2000

Mechanical fit-out.

December 1999
— March 2000

Prestressing is applied.

May 2000

Dock is flooded and the structure then towed.

1 June 2000

The concrete gravity base structure is installed.

17 March 2001

Topside installation.

16 October 2001

Inauguration by President Gloria Macapagal-Arroyo.

Relevant Web Sites

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20003469
  • Published on:
    03/06/2002
  • Last updated on:
    04/01/2016
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine