General Information
Other name(s): | Kigongo–Busisi Bridge |
---|---|
Beginning of works: | 7 December 2019 |
Completion: | October 2024 |
Status: | in use |
Project Type
Function / usage: |
Road bridge |
---|---|
Structure: |
Four-span extradosed bridge |
Support conditions: |
for registered users |
Material: |
Prestressed concrete bridge |
Material: |
Structurae Plus/Pro - Subscribe Now! |
Secondary structure(s): |
Structurae Plus/Pro - Subscribe Now! |
Material: |
Structurae Plus/Pro - Subscribe Now! |
Secondary structure(s): |
Structurae Plus/Pro - Subscribe Now! |
Location
Technical Information
Dimensions
total length | 3 000 m | |
number of spans | 66 | |
number of lanes | 2 x 2 | |
roadway / carriageway width | 2 x 9.5 m | |
walkway width | 2 x 2.5 m | |
deck | deck width | 28.45 m |
approach viaduct Busisi | ||
---|---|---|
total length | 1 240 m | |
span lengths | 31 x 40 m | |
approach viaduct Kigongo | ||
total length | 1 240 m | |
span lengths | 31 x 40 m | |
approach viaducts | ||
deck | number of longitudinal girders | 13 |
piles | diameter | 1.5 m |
number | 720 m | |
main bridge | ||
total length | 520 m | |
span lengths | 100 m - 2 x 160 m - 100 m | |
vertical navigation clearance | 17 m | |
horizontal navigation clearance | 2 x 74 m | |
deck | deck depth | 3.2 - 5.4 m |
girder depth | 1.8 m | |
piles | diameter | 2.5 m |
number | 84 | |
pylons | pylon height (above deck) | 18.856 m |
Quantities
approach viaducts | ||
---|---|---|
deck | number of precast segments | 806 |
Materials
deck |
prestressed concrete
|
---|---|
piers |
reinforced concrete
|
pylons |
reinforced concrete
|
abutments |
reinforced concrete
|
Participants
Currently there is no information available about persons or companies having participated in this project.
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- (2024): Construction of J.P. Magufuli Extradosed Cable-Stayed Bridge (3.0km) at Mwanza, Tanzania near Kigongo/Busisi Ferry.. Presented at: IABSE Congress: Beyond Structural Engineering in a Changing World, San José, Cost Rica, 25-27 Seotember 2024, pp. 1004-1012.
- About this
data sheet - Structure-ID
20090374 - Published on:
25/01/2025 - Last updated on:
26/01/2025