General Information
Project Type
Structure: |
Tunnel |
---|---|
Function / usage: |
Railroad (railway) tunnel |
Location
Location: |
Båstad, Skåne län, Sweden |
---|---|
Coordinates: | 56° 21' 43" N 12° 48' 20" E |
Coordinates: | 56° 25' 27.81" N 12° 53' 17.54" E |
Technical Information
Dimensions
tube 1 | tunnel length | 8 722 m |
tube 2 | length | 8 710 m |
Cost
cost of construction | ca. Euro 450 000 000 |
Chronology
1997 | 2 000 tons of Rhoca-Gil (caulking agent) used in construction pollute the groundwater around the site. Construction is halted. |
---|---|
2003 | Construction to re-start. |
2011 | Expected completion. |
Participants
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Advanced Ground Freezing at the Hallandsås Project, Sweden. In: Geomechanik und Tunnelbau, v. 1, n. 5 ( 2008), pp. 512-517. (2008):
- Premier partenariat majeur entre Vinci et Skanska à Hallandsas. In: Le Moniteur des Travaux Publics et du Bâtiment, n. 5313 (23 September 2005), pp. 17. (2005):
- Situation beim Hallandsastunnel in Schweden. In: Bauingenieur, v. 83, n. 5 (May 2008), pp. 749. (2008):
- Situation beim Hallandsastunnel in Schweden, Bauen und Umwelt. In: Bauingenieur, v. 75, n. 12 (December 2000), pp. 43+. (2000):
- Tunnel d'Hallandsas. Creusement sous haute surveillance. In: Le Moniteur des Travaux Publics et du Bâtiment, n. 5328 (6 January 2006), pp. 50-51. (2006):