General Information
Project Type
Structure: |
Tunnel |
---|---|
Function / usage: |
High-speed rail tunnel |
Construction method: |
Slurry-shield machine |
Location
Location: |
Leiderdorp, South Holland, Netherlands Hazerswoude-Dorp, South Holland, Netherlands |
---|---|
Part of: | |
Coordinates: | 52° 9' 37.19" N 4° 33' 27.23" E |
Coordinates: | 52° 5' 32.49" N 4° 33' 53.14" E |
Technical Information
Dimensions
total length | 8 600 m | |
tunnel length | 7 160 m | |
interior diameter | 13.20 | |
TBM | total length | 120 m |
total weight | 3 520 t | |
excavation diameter | 14.87 m | |
length of shield | 12.40 m | |
weight of shield | 1 800 t | |
total power | 9 540 kW | |
power at cutter head | 3 500 kW | |
total thrust | 19 x 2 × 485 = 18 430 t | |
torque at cutter head | 136 000 kNm | |
cutter head speed | 0 - 1.4 / min. | |
nominal flow rate | 2 500 m³/h |
Quantities
reinforcing steel | 42 000 t | |
sheet piling | 43 300 m² | |
walls in trench | 84 900 m³ | |
prefabricated piles | 33 650 m | |
concrete for tunnel elements | 211 900 m³ | |
total excavated volume | 1 950 000 m³ | |
submerged concrete volume | 141 300 m³ | |
reinforced concrete volume | 113 900 m³ |
Cost
cost of construction | Dutch guilder 940 000 000 |
Materials
tunnel structure |
precast reinforced concrete
|
---|
Chronology
Beginning of 1999 | Invitation to tender. |
---|---|
17 December 1999 | The contract is signed. |
Participants
Client
Design
Structural engineering
- Bouygues Travaux Publics (tunnel)
Subconsultant
- Tunnel Engineering Consultants (access ramps)
Co-contractor
Foundations
Material supplier
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Breakthrough at the Groene Hart Tunnel. In: Felsbau, v. 22, n. 2 ( 2004), pp. 67.
- Challenges piling up!. In: News. The VSL-Intrafor Magazine, v. 13, n. 2 ( 2002), pp. 19.
- Experience with Design Build Contract of the Green Heart Tunnel. Presented at: 28th AITES- ITA World Tunnel Congress, Sydney, 02.-08.03.2002. (2002):
- Fundamental research program High Speed Line Bored Tunnel Green Hart. Presented at: KivI, 1999, TU Delft,. (1999):
- Groene Hart (Pays-Bas). Travaux de fondations: un chantier à grande vitesse. In: Travaux, n. 785 (April 2002), pp. 58-61. (2002):