General Information
Name in local language: | Viaducto Gilberto Borja Navarrete |
---|---|
Other name(s): | San Marcos Bridge; San Marcos Viaduct |
Completion: | November 2012 |
Status: | in use |
Project Type
Function / usage: |
Motorway bridge / freeway bridge |
---|---|
Structure: |
Haunched girder bridge |
Construction method: |
Balanced cantilever method |
Material: |
Prestressed concrete bridge |
Structure: |
Box girder bridge |
Material: |
Structurae Plus/Pro - Subscribe Now! |
Location
Technical Information
Dimensions
main span | 180 m | |
total length | 850 m | |
span lengths | 57 m - 98 m - 3 x 180 m - 98 m - 57 m | |
number of spans | 7 | |
height above valley floor or water | 220 m | |
number of lanes | 2 x 2 | |
deck | deck depth | 3.6 - 10.0 m |
deck width | 18.7 m | |
roadway / carriageway width | 2 x 8.52 m | |
pier P2 | height | 76.11 m |
pier P3 | height | 166 m |
pier P4 | height | 208.23 m |
pier P5 | height | 121 m |
piles | diameter | 1.200 m / 1.500 m |
Quantities
volume of extracted material | 231 200 m³ | |
deck | concrete volume | 16 055 m³ |
prestressing steel | 770 t | |
reinforcing steel | 2 268 t | |
piles | total length of piles | 904 m (ø 1.5 m) + 261 m (ø 1.2 m) |
substructure | concrete volume | 19 629 m³ |
reinforcing steel | 3 516 t |
Materials
deck |
prestressed concrete
|
---|---|
piers |
reinforced concrete
|
abutments |
reinforced concrete
|
Participants
Owner
Design
Co-contractor
Prestressing
Formwork & shoring
Relevant Web Sites
Relevant Publications
- Gilberto Borja Navarrete Viaduct. In: Hormigón y acero, v. 66, n. 275 (1st Quarter 2015), pp. e1-e20. (2015):
- Viaducto Gilberto Borja Navarrete. In: Hormigón y acero, v. 66, n. 275 (1st Quarter 2015), pp. 1-21. (2015):
- About this
data sheet - Structure-ID
20052334 - Published on:
24/01/2010 - Last updated on:
13/12/2024