General Information
Name in local language: | Mainbrücke Gemünden |
---|---|
Completion: | 31 October 2018 |
Duration of works: | 22 months |
Status: | in use |
Project Type
Function / usage: |
Road bridge |
---|---|
Structure: |
Haunched girder bridge |
Plan view: |
Structurae Plus/Pro - Subscribe Now! |
Material: |
Material hybrid bridge main bridge: Steel-reinforced concrete composite bridge |
Structure: |
main bridge: Box girder bridge |
Material: |
Structurae Plus/Pro - Subscribe Now! approach viaducts: Prestressed concrete bridge |
Location
Location: |
Gemünden am Main, Main-Spessart, Bavaria, Germany |
---|---|
Crosses: |
|
Coordinates: | 50° 3' 20.24" N 9° 41' 5.80" E |
Technical Information
Dimensions
roadway / carriageway width | 7.50 | |
approach viaduct | ||
---|---|---|
deck depth | 1.80 m | |
main bridge | ||
deck depth | 1.80 - 6.00 m | |
total length | 312.38 m | |
span lengths | 34.16 m - 47.32 m - 110.00 m - 50.95 m - 37-98 m - 31.97 m | |
number of spans | 6 |
Materials
piers |
reinforced concrete
|
---|---|
deck of main bridge |
composite steel-reinforced concrete
|
deck of approach viaduct |
prestressed concrete
|
abutments |
reinforced concrete
|
Participants
Owner
Design
Traffic engineering
Structural engineering
Checking engineering
Co-contractor
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Mainbrücke Gemünden. Neuer Überbau auf alten Pfeilern. In: Brückenbau, v. 12, n. 1-2 ( 2020), pp. 44-51. (2020):
- About this
data sheet - Structure-ID
20079562 - Published on:
25/06/2020 - Last updated on:
25/06/2020