General Information
Duration of works: | 32 months |
---|---|
Status: | in use |
Project Type
Structure: |
Girder bridge |
---|---|
Construction method: |
Incremental launching |
Material: |
Prestressed concrete bridge |
Location
Location: |
Cape Town, Western Cape, South Africa |
---|
Technical Information
Dimensions
total length | 504 m |
Cost
cost of construction | South African rand 2 400 000 |
Materials
deck |
prestressed concrete
|
---|
Participants
Relevant Web Sites
There currently are no relevant websites listed.
- About this
data sheet - Structure-ID
20020976 - Published on:
27/04/2006 - Last updated on:
05/02/2016