0
  • DE
  • EN
  • FR
  • International Database and Gallery of Structures

Advertisement

General Information

Name in local language: Elbebrücke Dömitz
Beginning of works: August 1991
Completion: December 1992
Duration of works: 17 months
Status: in use

Project Type

Structure: main bridge:
Tied-arch bridge
approach viaducts:
Single-cell box girder bridge
Function / usage: Road bridge
Material: main bridge:
Steel bridge
Structurae Plus/Pro - Subscribe Now!
approach viaducts:
Prestressed concrete bridge

Location

Location: , , , ,
Crosses:
  • Elbe River
Replaces: Dömitz Elbe Bridge (1936)
Coordinates: 53° 8' 34.14" N    11° 13' 41.97" E
Show coordinates on a map

Technical Information

Dimensions

total length 969.7 m
span lengths 33.0 m - 11 x 40.5 m - 52.3 m - 55.0 m - 58.4 m - 59.0 m - 178.0 m - 50.0 m - 38.5 m
number of spans 19
bridge surface 14 885 m²
arch arch span 178.0 m

Quantities

structural steel 1 831 t
concrete volume 24 300 m³
prestressing steel 480 t

Design Loads

live load Brückenklasse 60/30
design code(s) DIN 1072

Cost

cost of construction ca. German Mark 52 400 000
arch cost of construction per m² German Mark 7 000
approach viaducts
cost of construction per m² German Mark 2 600

Materials

piers reinforced concrete
arch steel
deck of approach viaducts prestressed concrete
abutment reinforced concrete

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

More publications...
  • About this
    data sheet
  • Structure-ID
    20001120
  • Published on:
    28/10/2000
  • Last updated on:
    20/02/2018
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine