Diepmannsbach Bridge at Remscheid-Lennep

General Information

Name in local language: Diepmannsbach-Talbrücke Remscheid-Lennep
Beginning of works: November 1992
Completion: April 1995
Duration of works: 30 months
Status: in use

Project Type

Location

Location: , ,
Carries:
  • Autobahn A1
Crosses:
  • Diepmann Creek
Part of:
Next to: Diepmannsbach Bridge at Remscheid-Lennep (1955)
Coordinates: 51° 11' 33.64" N    7° 14' 15.58" E
Show coordinates on a map

Technical Information

Dimensions

total length 292.644 m
span lengths 6 x 48.774 m
number of spans 6
bridge surface 5 487 m²
deck deck width 18.75 m
piles diameter 1.50 m

Quantities

structural steel 1 110 t
abutments concrete volume 1 305 m³
reinforcing steel 59 t
deck structural steel 1 110 t
deck slab concrete volume 2 070 m²
reinforcing steel 530 t
foundation slab concrete volume 489 m³
reinforcing steel 30 t
pier heads concrete volume 159 m³
reinforcing steel 28 t
piers concrete volume 2 507 m³
reinforcing steel 76 t
pile caps concrete volume 874 m³
reinforcing steel 54 t
piles reinforcing steel 49 t
total length of piles 500 m

Cost

cost of construction German Mark 23 300 000

Materials

deck composite steel-reinforced concrete
piers reinforced concrete
foundations reinforced concrete
abutments reinforced concrete

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20001164
  • Published on:
    15/12/2000
  • Last updated on:
    07/12/2016