General Information
Name in local language: | Viaduc de Compiègne |
---|---|
Beginning of works: | 2007 |
Completion: | 2009 |
Status: | in use |
Project Type
Structure: |
Box girder bridge |
---|---|
Construction method: |
Precast segmental construction with temporary cable-stays |
Material: |
Prestressed concrete bridge |
Function / usage: |
Road bridge |
Material: |
Structurae Plus/Pro - Subscribe Now! |
Location
Location: |
Choisy-au-Bac, Oise (60), Hauts-de-France, France Clairoix, Oise (60), Hauts-de-France, France |
---|---|
Crosses: |
|
Coordinates: | 49° 26' 10" N 2° 50' 57" E |
Technical Information
Dimensions
main span | 66.5 m | |
total length | 2 140 m | |
standard span lengths | 58.7 m | |
piers | deck depth at abutments | 35 |
Quantities
concrete volume | 31 000 m³ | |
prestressing steel | 842 t | |
reinforcing steel | 5 600 t | |
number of precast segments | 801 | |
total length of piles | 3 270 m (ø 1200, 1400 & 1600 mm) |
Materials
deck |
prestressed concrete
|
---|---|
piers |
reinforced concrete
|
abutments |
reinforced concrete
|
Participants
Architecture
- AEI - Architecture Environnement Infrastructures
- Pierre Loyer (architect)
- Rodrigue de Peñaranda de Franchimont (architect)
Structural engineering
Co-contractor
Subcontractor
Foundations
Prestressing
Reinforcing steel
Bearings
Formwork & shoring
Formwork
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Des voussoirs en bétons posés à l'avencement. In: Construction moderne ( 2008), pp. 27-29. (2008):
- Plain sailing. A new viaduct being built in France crosses the alluvial plains of two rivers. In: Bridge Design & Engineering, v. 15, n. 55 (2nd Quarter 2009), pp. 25.
- Le viaduc de Compiègne sur la RN31. Les Eurocodes en marche sur un ouvrage construit à l'avancement [Partie 1]. In: Ouvrages d'art, n. 63 (March 2010), pp. 2-13. (2010):
- About this
data sheet - Structure-ID
20040045 - Published on:
17/10/2008 - Last updated on:
22/08/2018