General Information
Completion: | 2004 |
---|---|
Status: | in use |
Project Type
Structure: |
Girder bridge |
---|---|
Function / usage: |
Motorway bridge / freeway bridge |
Construction method: |
Incremental launching |
Material: |
Prestressed concrete bridge |
Support conditions: |
for registered users |
Location
Location: |
Mungyeong, North Gyeongsang, South Korea |
---|
Technical Information
Dimensions
main span | 75 m | |
total length | 705 m / 690 m | |
horizontal radius of curvature | 0 m | |
deck | deck width | 2 x 12.145 m |
Quantities
prestressing steel | 692 t |
Materials
substructure |
reinforced concrete
|
---|---|
deck |
prestressed concrete
|
Participants
Owner
Design
Co-contractor
Relevant Web Sites
There currently are no relevant websites listed.
- About this
data sheet - Structure-ID
20010753 - Published on:
28/11/2003 - Last updated on:
05/02/2016