Name in local language: | Mittellandkanal-Brücke Bergfriede |
---|---|
Beginning of works: | 9 February 2019 |
Completion: | June 2021 |
Status: | in use |
Project Type
Function / usage: |
Road bridge |
---|---|
Plan view: |
Structurae Plus/Pro - Subscribe Now! |
Structure: |
Tied-arch bridge |
Support conditions: |
Structurae Plus/Pro - Subscribe Now! |
Material: |
Steel bridge |
Construction method: |
Structurae Plus/Pro - Subscribe Now! |
Location
Location: |
Oebisfelde-Weferlingen, Börde, Saxony-Anhalt, Germany |
---|---|
Crosses: |
Mittelland Canal (1938)
|
Coordinates: | 52° 27' 26.72" N 11° 4' 21.19" E |
Technical Information
Dimensions
span | 117.00 m | |
bridge surface | 1 357.20 m² | |
arches | rise | 18.00 m |
angle of inclination | 10° | |
spacing | 8.525 - 14.875 m | |
deck | deck width | 11.60 m |
deck slab thickness | 0.30 m | |
distance between cross-beams | 3.25 m | |
hangers | diameter | 0.130 m |
number | 2 x 10 | |
spacing | 9.75 m | |
piles | diameter | 1.20 - 2.40 m |
length | 18.00 m | |
number | 2 x 11 |
Quantities
substructure | concrete volume | 1 100 m³ |
reinforcing steel | 230 t | |
superstructure | structural steel | 1 125 t |
concrete volume | 600 m³ | |
reinforcing steel | 130 t |
Design Loads
live load | LM1 | |
design code(s) | DIN EN 1991-2 |
Materials
arches |
steel
(S 355)
|
---|---|
deck slab |
reinforced concrete
(C 35/45)
|
abutments |
reinforced concrete
(C 30/37)
|
cross beams |
steel
(S 355)
|
main girders |
steel
(S 355)
|
Participants
Currently there is no information available about persons or companies having participated in this project.
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Brücken und Tunnel der Bundesfernstraßen 2022. Bundesministerium für Verkehr und digitale Infrastruktur, Berlin (Germany), 2022, pp. 75-87.
- About this
data sheet - Structure-ID
20085741 - Published on:
20/04/2023 - Last updated on:
20/04/2023