Beginning of works: | 2008 |
---|---|
Status: | under construction |
Project Type
Structure: |
Gravity dam |
---|---|
Material: |
Concrete dam |
Function / usage: |
Fresh water dam |
Location
Technical Information
Dimensions
height | 49 m | |
crest thickness | 8 m | |
dam volume | 99 451 m³ |
Excerpt from Wikipedia
The Balli Dam is a gravity dam under construction on the Ortasu River (a tributary of the Hezil River) in Uludere district of Şırnak Province, southeast Turkey. Under contract from Turkey's State Hydraulic Works, construction on the dam began in 2008 and a completion date has not been announced.
The reported purpose of the dam is water storage and it can also support an 8.36 MW hydroelectric power station in the future. Another purpose of the dam which has been widely reported in the Turkish press is to reduce the freedom of movement of Kurdistan Workers' Party (PKK) militants. Blocking and flooding valleys in close proximity to the Iraq–Turkey border is expected to help curb cross-border PKK smuggling and deny caves in which ammunition can be stored. A total of 11 dams along the border; seven in Şırnak Province and four in Hakkâri Province were implemented for this purpose. In Şırnak they are the Silopi, Şırnak and Uludere Dams downstream of the Balli Dam and the Kavşaktepe, Musatepe and Çetintepe Dams upstream on the Ortasu River. In Hakkari are the Gölgeliyamaç (since cancelled) and Çocuktepe Dams on the Güzeldere River and the Aslandağ and Beyyurdu Dams on the Bembo River.
Text imported from Wikipedia article "Balli Dam" and modified on July 23, 2019 according to the CC-BY-SA 4.0 International license.
Participants
Currently there is no information available about persons or companies having participated in this project.
Relevant Web Sites
- About this
data sheet - Structure-ID
20072304 - Published on:
15/12/2016 - Last updated on:
15/12/2016