General Information
| Name in local language: | Tunnel Aubing |
|---|---|
| Official designation: | Bw96-1 |
| Beginning of works: | October 2002 |
| Completion: | December 2005 |
| Duration of works: | 29 months |
| Status: | in use |
Project Type
| Structure: |
Tunnel |
|---|---|
| Function / usage: |
Road tunnel |
Location
| Location: |
Aubing-Lochhausen-Langwied, Munich, Bavaria, Germany |
|---|---|
| Part of: | |
| Coordinates: | 48° 9' 27.84" N 11° 24' 6.52" E |
| Coordinates: | 48° 10' 14.13" N 11° 25' 11.29" E |
Technical Information
Dimensions
| width | 30.40 m | |
| total length | 2 425 m | |
| tunnel length | 1 935 m | |
| roadway / carriageway width | 2 x 12.25 m |
Quantities
| concrete volume | 152 000 m³ | |
| reinforcing steel | 25 500 t | |
| excavated material | 430 000 m³ |
Cost
| cost of construction | ca. Euro 91 000 000 |
Participants
Owner
Client
Object planning
Original design
- Brüninger & Co Engineering GmbH
- Schmitt Stumpf Frühauf und Partner Ingenieurgesellschaft im Bauwesen mbH
Structural engineering
Checking engineering
- Walter Streit (checking engineer)
Co-contractor
Construction supervision
Relevant Web Sites
There currently are no relevant websites listed.
Relevant Publications
- Brücken und Tunnel der Bundesfernstraßen 2007. Deutscher Bundes-Verlag, Cologne (Germany), ISBN 978-3-935064-53-8, 2007, pp. 141-155.
- About this
data sheet - Structure-ID
20029106 - Published on:
11/07/2007 - Last updated on:
27/09/2025