General Information
Project Type
Function / usage: |
Waste incinerator |
---|---|
Material: |
roof: Steel structure |
Structure: |
roof: Space truss |
Location
Location: |
Copenhagen, Hovedstaden, Denmark |
---|---|
Address: | Vindmøllevej 6 |
Coordinates: | 55° 41' 4.53" N 12° 37' 12.49" E |
Technical Information
Quantities
structural steel | 6 500 t |
Materials
truss |
steel
|
---|
Excerpt from Wikipedia
Amager Bakke (Amager Hill) also known as Amager Slope or Copenhill, is a combined heat and power waste-to-energy plant in Amager, Copenhagen, Denmark. It opened in 2017, and partially replaced the nearby old incineration plant in Amager, which is in the process of being converted from coal to biomass (expected finished 2020). The two plants play a major role in Copenhagen's ambitions of being zero carbon by 2025.
Construction and technicalities
The plant opened on 30 March 2017. It is estimated to cost $670 million, and is expected to burn 400,000 tons of municipal solid waste annually. It was designed by Bjarke Ingels Group with a 85 m (279 ft) tall sloped roof that doubles as year-round artificial ski slope, hiking slope and climbing wall, which opened to the public in early 2019. Technically, it is designed to change between operating modes, producing 0-63 MW electricity and 157-247 MW district heating, depending on the local heat demand and power price. It produces more clean water than it uses. Because of filtration and other technologies, sulphur emission is expected to be reduced by 99.5% and NOx by about 90%, and it is claimed to be the cleanest incineration plant in the world.
A special feature of this facility will be that the chimney is intended to not emit its exhaust continuously, but instead in the form of "smoke" rings (consisting of water vapour rather than actual smoke).
Operational history
On September 7, 2018 all waste treatment and energy production was stopped for 17 days to fix a design flaw in the compensators of the low pressure steam system.
Text imported from Wikipedia article "Amager Bakke" and modified on July 23, 2019 according to the CC-BY-SA 4.0 International license.
Participants
Relevant Web Sites
Relevant Publications
- Modellbasierte Planung und Bauausführung des räumlichen Stahltragwerkes bei der Müllverbrennungsanlage Amager Bakke. In: Stahlbau, v. 85, n. 10 (October 2016), pp. 644-653. (2016):
- About this
data sheet - Structure-ID
20072271 - Published on:
07/12/2016 - Last updated on:
15/10/2019