General Information
Project Type
Function / usage: |
Motorway / Freeway / Interstate |
---|
Location
km | Name |
Technical Information
Dimensions
total length | 170 km |
Cost
cost of construction | ca. Euro 650 000 000 |
Chronology
27 January 2003 | Inauguration of the last section of the A84. |
---|
Participants
Currently there is no information available about persons or companies having participated in this project.
Relevant Web Sites
Relevant Publications
- A84. DDE en trio (1ère partie). In: Revue Générale des Routes, n. 814 (February 2003), pp. 6-7. (2003):
- Autoroute A84 en Ile-et-Vilaine. Gestion des dépôts de matériaux excédentaires en zone agricole. In: Travaux, n. 740 (March 1998), pp. 28-33. (1998):
- About this
data sheet - Structure-ID
10000177 - Published on:
01/01/2003 - Last updated on:
28/05/2021