A 113 Teltowkanal Bridge

General Information

Beginning of works: 2002
Completion: 2004
Duration of works: 31 months
Status: in use

Project Type

Location

Location: , , ,
, , ,
, , ,
Crosses:
  • Teltowkanal
Part of:
Coordinates: 52° 25' 35.28" N    13° 31' 12.45" E
Show coordinates on a map

Technical Information

Dimensions

total length 149.30 m
span lengths 66.50 m - 82.80 m
bridge surface 5 240 m²
deck deck width 31.70 m

Quantities

substructure concrete volume 6 150 m³
reinforcing steel 430 t
superstructure structural steel 2 315 t
concrete volume 1 650 m³
reinforcing steel 370 t

Cost

cost of construction Euro 12 200 000

Materials

deck slab reinforced concrete
girders steel

Advertisement

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20034772
  • Date created
    27/02/2008
  • Last Update
    05/02/2016