0
  • DE
  • EN
  • FR
  • International Database and Gallery of Structures

Advertisement

General Information

Beginning of works: 2002
Completion: 2004
Duration of works: 31 months
Status: in use

Project Type

Location

Location: , , ,
, , ,
, , ,
Crosses:
  • Teltowkanal
Part of:
Coordinates: 52° 25' 35.28" N    13° 31' 12.45" E
Show coordinates on a map

Technical Information

Dimensions

total length 149.30 m
span lengths 66.50 m - 82.80 m
number of spans 2
bridge surface 5 240 m²
deck deck width 31.70 m

Quantities

substructure concrete volume 6 150 m³
reinforcing steel 430 t
superstructure structural steel 2 315 t
concrete volume 1 650 m³
reinforcing steel 370 t

Cost

cost of construction Euro 12 200 000

Materials

deck slab reinforced concrete
girders steel

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20034772
  • Published on:
    27/02/2008
  • Last updated on:
    24/08/2020
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine