Elegant arched bridge spanning the Elbe

Below the Waldschloesschen area of the Elbe Valley in Dresden, a road bridge is currently being realised that will connect the eastern and southern districts of the city with areas in the north. PERI has planned and is supplying the formwork for the superstructure of the steel composite bridge.

The Waldschloesschen Bridge has a total length of around 635 m. Two steel arches with a span of 148 m reach of a height of almost 26 m above the Elbe and carry the central part of the bridge. The foreshore bridges account for a large part of the structure’s length with V-shaped double piers in place to support the superstructure.

Economical solution thanks to rentable system components

The standard cross-section of the bridge in the arched area has an overall width of approximately 28 m. A 14-metre wide carriageway has been constructed between the two steel arches consisting of four lanes whilst 4.45 m wide pedestrian and cycle lanes cantilever outwards on both sides of the bridge respectively.

The customised formwork solution for the superstructure was developed by PERI engineers on the basis of the VARIOKIT engineering construction kit. With the standardized, rentable system components and site-compliant connecting parts taken from the construction kit, bridges can be economically realised optimally adapted to match the respective project requirements. Essential system components for the raised formwork construction suspended on the steel structure used in Dresden are SRU steel walers and SLS heavy-duty spindles. The mounting points for the formwork units were planned before the production of the steel structure. The proven, high load-bearing and rigid GT 24 wooden lattice girders transfer the loads into the formwork units and allow large spans with minimal deflection. All system components used for the frame construction units are rentable resulting in a very cost-effective project-specific solution.

Rapid construction progress with a high utilization rate

In order to minimize deformations, a total of 21 casting segments were planned for the carriageway slab and cantilevers. In spite of the geometric changes found in the bridge construction, forming could be carried out with only two standard raised formwork units: the length of the units was planned so that that they could be easily combined in a number of ways for the construction of the sections. The raised formwork units mounted on-site by the consortium – ARGE Ingenieurbau Waldschoesschenbruecke – construction team are thus being used for almost the entire bridge structure.

Through the multiple usage of the raised formwork units and the utilisation of the VARIOKIT engineering construction kit, it is possible to move from one concreting section to the next without the need of any modification work. In addition, the units are relatively light, easy to handle and can be moved quickly and without complications. Thanks to the simple and user-friendly design, the construction team was able to familiarize itself very quickly with the operating sequences. As a result, the high degree of material utilisation and easy application make the formwork solution extremely cost-effective.

Services
Offered by

References

Dresden, Saxony, Germany (2013)

Structure Types

  • About this
    data sheet
  • Product-ID
    6055
  • Published on:
    09/10/2012
  • Last updated on:
    03/03/2020