Study on Key Construction Procedures of CRD Method for Re Shuitang No.3 Tunnel

Author(s):



Medium: journal article
Language(s): English
Published in: IOP Conference Series: Materials Science and Engineering, , n. 1, v. 711
Page(s): 012074
DOI: 10.1088/1757-899x/711/1/012074
Abstract:

Controlling the critical construction steps of the CRD method plays an important role in ensuring construction and ensuring construction safety. When using the CRD method for the construction of the Re Shuitang No. 3 tunnel, through the numerical simulation of the initial support structure and the temporary support structure during the tunnel construction process, it is concluded that the left upper step, the upper right step and the temporary support structure are obviously stressed. Construction steps. According to the analysis results, the surrounding rock of the vault should be strengthened in advance, and the second lining structure should be applied after the surrounding rock is stabilized.

Structurae cannot make the full text of this publication available at this time. The full text can be accessed through the publisher via the DOI: 10.1088/1757-899x/711/1/012074.
  • About this
    data sheet
  • Reference-ID
    10675402
  • Published on:
    29/05/2022
  • Last updated on:
    29/05/2022
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine