Simulation Analysis and Application of Super High-rise Tower Construction Process
Author(s): |
Yazhou Ou
Bao Chen Hongxue Jia Guanghua Yin Jiang Cao |
---|---|
Medium: | journal article |
Language(s): | English |
Published in: | Journal of Physics: Conference Series, 1 January 2022, n. 1, v. 2185 |
Page(s): | 012065 |
DOI: | 10.1088/1742-6596/2185/1/012065 |
Abstract: |
Wenzhou Lucheng Square Phase IV project, whose main tower reaching 378.8m high, belongs to the super high-rise building structure. Considering the influence of shrinkage and creep characteristics of concrete on vertical deformation differences of components, Midas Gen was used to simulate and analyze the whole construction process of the main tower. The analysis results of different working conditions are compared, the rationality of the construction scheme is checked and a general conclusion is drawn. |