El proceso constructivo del tramo atirantado del Puente de la Constitución de 1812 sobre la Bahía de Cádiz

Author(s):


Medium: journal article
Language(s): English, Spanish
Published in: Hormigón y acero, , n. 278-279, v. 67
Page(s): 101-109
DOI: 10.1016/j.hya.2015.12.005
Abstract:

Construction process of the 'Constitución de 1812' cable stayed Bridge over the Cadiz Bay

Balanced cantilever method has been use to erect the cable-stayed section of the "Constitución de 1812" bridge over Cadiz Bay. Standard segments are 20 m long and 34 m width and weigh 4.000 kN.The construction sequence has been determined by the ultimate resistance of the tower that must resist the unbalanced bending moments at both sides of the tower.

Keywords:
balanced cantilever segment Construction sequence Cable-stayed deck Erection procedure

Structures and Projects

Structurae cannot make the full text of this publication available at this time. The full text can be accessed through the publisher via the DOI: 10.1016/j.hya.2015.12.005.
  • About this
    data sheet
  • Reference-ID
    10075453
  • Published on:
    27/03/2018
  • Last updated on:
    07/10/2018
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine