El proceso constructivo del tramo atirantado del Puente de la Constitución de 1812 sobre la Bahía de Cádiz
Auteur(s): |
Conchita Lucas Serrano
Antonio Martínez Cutillas Juan Antonio Navarro González-Valerio |
---|---|
Médium: | article de revue |
Langue(s): | anglais, espagnol |
Publié dans: | Hormigón y acero, janvier 2016, n. 278-279, v. 67 |
Page(s): | 101-109 |
DOI: | 10.1016/j.hya.2015.12.005 |
Abstrait: |
Construction process of the 'Constitución de 1812' cable stayed Bridge over the Cadiz BayBalanced cantilever method has been use to erect the cable-stayed section of the "Constitución de 1812" bridge over Cadiz Bay. Standard segments are 20 m long and 34 m width and weigh 4.000 kN.The construction sequence has been determined by the ultimate resistance of the tower that must resist the unbalanced bending moments at both sides of the tower. |