0
  • DE
  • EN
  • FR
  • International Database and Gallery of Structures

Advertisement

Estimation Of Task Completion Times With The Use Of The PERT Method On The Example Of A Real Construction Project

Author(s):


Medium: journal article
Language(s): English
Published in: Archives of Civil Engineering, , n. 3, v. 61
Page(s): 51-62
DOI: 10.1515/ace-2015-0024
Abstract:

The article presents briefly several methods of working time estimation. However, three methods of task duration assessment have been selected to investigate working time in a real construction project using the data collected from observing workers laying terrazzo flooring in staircases. The first estimation has been done by calculating a normal and a triangular function. The next method, which is the focus of greatest attention here, is PERT. The article presents a way to standardize the results and the procedure algorithm allowing determination of the characteristic values for the method. Times to perform every singular component sub-task as well as the whole task have been defined for the collected data with the reliability level of 85%. The completion time of the same works has also been calculated with the use of the KNR. The obtained result is much higher than the actual time needed for execution of the task calculated with the use of the previous method. The authors argue that PERT is the best method of all three, because it takes into account the randomness of the entire task duration and it can be based on the actual execution time known from research.

Structurae cannot make the full text of this publication available at this time. The full text can be accessed through the publisher via the DOI: 10.1515/ace-2015-0024.
  • About this
    data sheet
  • Reference-ID
    10476897
  • Published on:
    25/11/2020
  • Last updated on:
    25/11/2020
 
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine