Case Study as to the Effectiveness of Dispute Review Boards on the Central Artery/Tunnel Project
Author(s): |
Kathleen M. Harmon
(President, Harmon/York Associates, Inc., 65 Railroad Ave., Ridgefield Park, NJ 07660.)
|
---|---|
Medium: | journal article |
Language(s): | English |
Published in: | Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, February 2009, n. 1, v. 1 |
Page(s): | 18-31 |
DOI: | 10.1061/(asce)1943-4162(2009)1:1(18) |