0
  • DE
  • EN
  • FR
  • International Database and Gallery of Structures

Advertisement

Replacement of the Schwelmetal Viaduct in Germany – Use of BIM

 Replacement of the Schwelmetal Viaduct in Germany – Use of BIM
Author(s): , ,
Presented at IABSE Congress: The Evolving Metropolis, New York, NY, USA, 4-6 September 2019, published in , pp. 1836-1843
DOI: 10.2749/newyork.2019.1836
Price: € 25.00 incl. VAT for PDF document  
ADD TO CART
Download preview file (PDF) 0.19 MB

The Schwelmetal Viaduct is part of the federal highway A1 near Wuppertal, Germany. It spans over a major railway line, another federal and local road, as well as the Schwelme River. The scope inclu...
Read more

Bibliographic Details

Author(s): (Arup Deutschland GmbH)
(Arup Deutschland GmbH)
(HOCHTIEF Infrastructure GmbH)
Medium: conference paper
Language(s): English
Conference: IABSE Congress: The Evolving Metropolis, New York, NY, USA, 4-6 September 2019
Published in:
Page(s): 1836-1843 Total no. of pages: 8
Page(s): 1836-1843
Total no. of pages: 8
DOI: 10.2749/newyork.2019.1836
Abstract:

The Schwelmetal Viaduct is part of the federal highway A1 near Wuppertal, Germany. It spans over a major railway line, another federal and local road, as well as the Schwelme River. The scope includes the demolition of the existing 207 m long viaduct built in the 1960s while all traffic on and below the bridge must keep flowing. Moreover, the highly confined space allows for minimal tolerances and basically no extra construction space.

A very elaborate demolition and erection scheme has been developed to minimize traffic interruption. BIM has been chosen as planning tool to make sure the strict geometric restraints are not violated and a safe construction can be ensured. The whole design and construction process is BIM supported - including the use of BIM for all progress meetings with the client DEGES. This is the first time BIM is used for the construction of a major highway bridge in Germany.

This paper describes the developed demolition and erection sequence and shows the practical issues arising when using BIM as a planning tool and how the process can be optimized in the future.

Keywords:
composite bridge demolition BIM bridge replacement