General Information

Beginning of works: November 2015
Completion: August 2016
Status: in use

Project Type

Location

Location: , , ,
Crosses:
  • Wiese River
Replaces: Lörrach Footbridge (1983)
Coordinates: 47° 37' 50.56" N    7° 39' 59.12" E
Show coordinates on a map

Technical Information

Dimensions

total length 85.10 m
span lengths 23.80 m - 3.50 m - 57.80 m
deck width 2.80 m
bridge surface 238.28 m²

Quantities

substructure concrete volume 2.5 m³
reinforcing steel 1.5 t
superstructure structural steel 30 t
wood 146 m³

Design Loads

design code(s) DIN EN 1991-2

Cost

cost of construction Euro 980 000

Materials

truss glued laminated timber (glulam)
abutments reinforced concrete
pier steel

Advertisement

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20074770
  • Date created
    16/02/2018
  • Last Update
    06/04/2018