0
  • DE
  • EN
  • FR
  • International Database and Gallery of Structures

Advertisement

General Information

Beginning of works: 2003
Completion: 2007
Duration of works: 35 months
Status: in use

Project Type

Structure: Tunnel
Function / usage: Road tunnel

Location

Location: , , ,
Address: B 518
Coordinates: 47° 37' 25.57" N    7° 54' 17.40" E
Coordinates: 47° 37' 29.75" N    7° 54' 2.11" E
Show coordinates on a map

Technical Information

Dimensions

width 9.5 m
length 176 + 165 = 341 m

Quantities

concrete volume 6 300 m³
reinforcing steel 1 000 t
excavated material 30 000 m³
shotcrete 1 800 m²

Cost

gallery cost of construction Euro 2 090 000
overall structure cost of construction Euro 5 930 000
tunnel cost of construction Euro 2 810 000

Relevant Web Sites

There currently are no relevant websites listed.

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20048941
  • Published on:
    04/11/2009
  • Last updated on:
    24/07/2014
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine