General Information

Name in local language: Tretten bru
Completion: 15 June 2012
Status: collapsed (15 August 2022)

Project Type

Location

Location: , ,
Coordinates: 61° 18' 44.29" N    10° 18' 0.42" E
Show coordinates on a map

Technical Information

Dimensions

main span 70 m
width 10 m
total length 148 m
number of spans 3
number of lanes 2
piers number 2

Materials

truss timber
pier masonry
weathering steel
verticals (truss) weathering steel

Chronology

15 August 2022

In the morning, the bridge suddenly and completely collapses into the river and onto the E6 road. At the time of collapse a car and a trailer-truck were crossing the bridge. The trailer-truck had a weight of 48 tons in total which did not exceed the posted weight limit of 50 tons. The car driver was able to exit their car without assistance while the truck driver had to be rescued by emergency services an hour after the collapse.

Before the collapse, users had reported rocking of the bridge under large vehicle loads. Inspections in 2021 and 2022, however, did not find any issues.

17 August 2022

Demolition and removal of the collapsed bridge begins.

22 August 2022

The secotion on which the trailer-truck had gotten stuck during the collapse is lowered and the vehicle is driven off the bridge on its power.

Participants

Relevant Web Sites

Relevant Publications

  • About this
    data sheet
  • Structure-ID
    20090399
  • Published on:
    28/01/2025
  • Last updated on:
    28/01/2025
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine