Other name(s): Waiwhakaiho Arch Bridge
Beginning of works: 2009
Completion: 5 June 2010
Status: in use

Project Type

Location

Location: , ,
Crosses:
  • Waiwhakaiho River
Coordinates: 39° 2' 15.86" S    174° 6' 44.48" E
Show coordinates on a map

Technical Information

Dimensions

total length 88 m
arch rise 9.5 m
span 68.8 m
deck deck width 3.25 m

Materials

arch steel tubes
deck flooring concrete

Chronology

2007

Concept design.

2008

The design is selected and awarded.

2008 — 2009

Detailed design.

5 June 2010

Official opening.

Notes

The 85-ton steel superstructure was fabricated in a workshop. It was transported to the site in one piece where it was winched across the river and lifted onto the partially completed abutments. These were then completed and thus connected to the arch. Afterwards, deck and balustrade were installed.

Participants

Owner
Design
Geotechnical/geological experts
Checking engineering
Civil works
Steel construction

Relevant Web Sites

  • About this
    data sheet
  • Structure-ID
    20059925
  • Published on:
    04/05/2011
  • Last updated on:
    29/05/2023
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine