Beginning of works: April 1941
Completion: November 1941
Status: in use

Project Type

Function / usage: Experimental structure
Material: Concrete structure

Location

Location: , , ,
Address: General-Pape-Straße
Coordinates: 52° 29' 2.45" N    13° 22' 17.95" E
Show coordinates on a map

Technical Information

Dimensions

weight 12 650 t
height from ground level 14 m
depth below ground level > 18 m
shaft diameter 11 m
length ca. 20 m
top diameter 21 m
height 12 m

Cost

cost of construction Reichsmark 400 000

Materials

building structure concrete

Excerpt from Wikipedia

The Schwerbelastungskörper (German: "heavy load-bearing body"; a.k.a. Großbelastungskörper - GBK) is a hefty concrete cylinder in Berlin, Germany located at the intersection of Dudenstraße, General-Pape-Straße, and Loewenhardtdamm in the northwestern part of the borough of Tempelhof. It was erected in 1941–1942 by Hitler's chief architect Albert Speer to determine the feasibility of constructing large buildings on the area's marshy, sandy ground, specifically a massive triumphal arch on a nearby plot. The arch, which would be in the style of the Nazi architectural movement, was to be about three times as large as the Arc de Triomphe in Paris and was one component of a plan to redesign the center of Berlin as an imposing, monumental capital reflecting the spirit of the Third Reich as envisioned by Hitler.

Built by Dyckerhoff & Widmann AG in 1941 at a cost of 400,000 Reichsmark, the Schwerbelastungskörper consists of a foundation with a diameter of 11 m (36 ft) that reaches 18.2 m (60 ft) into the ground and contains rooms which once housed instruments to measure ground subsidence caused by the weight of the cylinder, which was estimated as equivalent to the load calculated for one pillar of the intended arch. On this foundation a cylinder 14 m (46 ft) high and 21 m (69 ft) in diameter weighing 12,650 tonnes was erected at street level. The entire construction puts 1.24 Mpa (180 psi) of pressure on an area of 100 m² (1,100 sq ft). If it were to sink less than 6 cm (2.4 in), the soil would be deemed sound enough for further construction without additional stabilization. The cylinder itself was to be subsequently buried under an artificial hill upon which the triumphal arch was to be erected, enabling a panoramic view down a new wide north-south axis to a huge assembly hall to be constructed near, and dwarfing the Brandenburg Gate.

Work on the new capital was soon discontinued because of World War II and measurements at the cylinder ceased in June 1944. An analysis of the meticulous measurements only took place in 1948, revealing that the cylinder had sunk some 19 cm (7.5 in) after two and a half years. The arch as conceived by Speer could only have been built after considerable prior stabilization of the ground.

Removal of the cylinder was considered after the war to create new building sites, but because of ist mass as well as nearby train tracks and apartment buildings the structure could not be safely demolished with explosives. Measurements of the subsidence were resumed and continued until 1977 under the auspices of the Technical University of Berlin as part of a project to compile data about the city's geologic foundation. Since 1995 the monumental cylinder has been protected as a historic monument. It is open to the public for viewing and guided tours.

Text imported from Wikipedia article "Schwerbelastungskörper" and modified on July 22, 2019 according to the CC-BY-SA 4.0 International license.

Participants

Relevant Web Sites

  • About this
    data sheet
  • Structure-ID
    20000944
  • Published on:
    30/10/2006
  • Last updated on:
    23/01/2022
Structurae cooperates with
International Association for Bridge and Structural Engineering (IABSE)
e-mosty Magazine
e-BrIM Magazine